Process

  • 1

    Initial Consultation On-Site

    Typical timeframe: ≈ 1 week

    Objective: Understand your goals, lifestyle, budget and vision while assessing the overall feasibility of the project.

    Key Activities:
    • Initial onsite consultation
    • Walk through the existing home
    • Discuss your goals, lifestyle and future needs
    • Understand budget expectations
    • Explore opportunities, ideas and design options
    • Explain the Equity Builders process

    Outcome: A clear understanding of your objectives and whether the project is suitable to progress to concept design.

  • 2

    Preliminary Concept Drawings

    Typical timeframe: 2 – 6 weeks*

    Objective: Develop an initial design concept that can be assessed both functionally and financially.

    Key Activities:
    • Obtain existing plans from council (or we can arrange this for you)
    • Referral to a trusted designer or draftsperson (if required)
    • Develop preliminary floor plans and elevations
    • Refine layouts and functionality
    • Align the concept with your vision

    Outcome: A preliminary design suitable for feasibility assessment.

  • 3

    Feasibility Assessment

    Typical timeframe: ≈ 1 week

    Objective: Determine whether the proposed concept aligns with your budget before progressing into detailed documentation.

    Key Activities:
    • Review preliminary concept drawings
    • Assess renovation complexity
    • Review structural implications
    • Consider site constraints
    • Assess level of finish
    • Prepare preliminary construction pricing using current market data and professional estimating systems

    Outcome: You receive an informed understanding of the likely investment required before committing to the next stage.

    Decision Point: Clarity before you invest in approvals and documentation. Learn more about our Feasibility Assessment.

  • 4

    Documentation & Approvals

    Typical timeframe: 8 – 20+ weeks* (Stages 4 & 5 often run concurrently)

    Objective: Coordinate all documentation, consultants and approvals required to prepare the project for construction.

    Key Activities (as applicable):
    • Feature & detail documentation
    • Structural engineering
    • Surveying
    • Soil testing
    • BASIX / NatHERS
    • Stormwater design
    • Hydraulic design (where required)
    • Town planning
    • Development Application (DA)
    • Complying Development Certificate (CDC)
    • Construction Certificate (CC)
    • Council approvals
    • Consultant coordination

    Outcome: All required documentation and approvals are obtained to allow construction to proceed.

    Typical investment: Varies between projects (typically between $10,000 – $20,000 for design plans, engineering, approvals, surveys and consultant fees). This is why we complete a Feasibility Assessment using preliminary concept drawings first, to ensure the project aligns with your budget before you invest in detailed documentation and approvals.

  • 5

    Fixtures & Finishes

    Typical timeframe: 2 – 6 weeks

    Objective: Finalise all of your selections prior to pricing.

    Key Activities:
    • Flooring
    • Tiles
    • Cabinetry finishes
    • Benchtops
    • Tapware
    • Plumbing fixtures
    • Appliances
    • Lighting
    • Paint colours
    • Internal and external finishes
    • Hardware and accessories

    Outcome: The project is priced using your actual selections rather than provisional allowances wherever possible.

  • 6

    Detailed Pricing

    Typical timeframe: 2 – 4 weeks

    Objective: Produce an accurate project cost based on completed documentation and confirmed selections.

    Key Activities:
    • Obtain subcontractor quotations
    • Obtain supplier pricing
    • Price all construction materials
    • Price your selections
    • Review labour requirements
    • Complete internal estimating review
    • Finalise project costing

    Outcome: A comprehensive and accurate project price supported by real quotations and current market rates.

  • 7

    Fixed Price Contract

    Typical timeframe: ≈ 1 week

    Objective: Provide you with a comprehensive Fixed Price Contract based on completed documentation and pricing.

    Key Activities:
    • Final scope review
    • Contract preparation
    • Review inclusions and exclusions
    • Present contract documentation
    • Execute building contract

    Outcome: A Fixed Price Contract that reflects the approved plans, confirmed selections and accurately priced scope of works.

  • 8

    Project Planning & Scheduling

    Typical timeframe: 1 – 2 weeks

    Objective: Prepare the project for a successful construction commencement.

    Key Activities:
    • Build the construction programme
    • Schedule subcontractors
    • Order long-lead materials
    • Confirm supplier lead times
    • Set up the job in our construction software
    • Upload project documentation
    • Establish project milestones
    • Prepare client communication schedule
    • Confirm site commencement

    Outcome: The project is fully coordinated, scheduled and ready for construction.

  • 9

    Construction Begins

    Typical timeframe: Project dependent

    With planning complete, construction begins with every stakeholder working from the same documentation, selections, schedule and agreed scope.

    This preparation creates greater certainty, improved communication and a more efficient construction process for everyone involved.

    * Timeframes vary depending on project complexity, consultant availability and council approval timeframes.

  • ✓

    After Construction: Walkthrough, Handover & Aftercare

    • Final Walkthrough: We inspect the completed work together, address any final touch-ups and confirm every detail aligns with your vision and our standards.
    • Handover: We walk you through your completed project and provide a handover package with all relevant documentation, including warranties, care instructions and contact information for any future needs.
    • Aftercare: Our team is available to answer questions throughout the maintenance period, and we check in 3–6 months after completion to ensure you are completely satisfied.

    Because great renovations don’t start with construction. They start with great pre-construction planning.

Scroll to Top
Call Now Button